Utility Requirements
Key Sheet

Abbreviation

Requirement

WTRCommunity water system. In subdivisions which are to be provided with a community water system, each Parcel within the proposed subdivision, or Parcel being Developed, must be supplied by a water distribution system, including service connections, and with adequate fire flow and protection, which is designed in accordance with the standards prescribed in the Design Standards Water Section.
WELLWhere a community water system is not available a proven water supply located on each parcel is permitted.
SWRCommunity sanitary sewer system.
SWRSEPSanitary sewer collection and disposal or Sanitary sewage effluent ground disposal in accordance with Part 2, Section 5.2 (o)(viii) of this bylaw.
DITCHDrainage collection and disposal system by open ditches and culverts.
STMClosed drainage collection and disposal system (i.e., a system other than open ditches). 
SLStreet lighting throughout the subdivision.
SLIStreet lighting at street intersections only.
OHOverhead electrical and communication wiring. 
UGUnderground electrical and communication wiring.
WCommunication and electrical wiring to conform to the highest standard of existing adjacent facilities

 

Table 1 - Utility Requirements

Utilities

(Refer to the Key Sheet Above)
Zone1WaterSewerDrainWiringLighting
A1WELLSWRSEPDITCHOHSLI
A2WELLSWRSEPDITCHOHSLI
RR1WTRSWRSEPDITCHOHSLI
RR2WTRSWRDITCHOHSLI
RU1WTRSWRSTMUGSL
RU2WTRSWRSTMUGSL
RU3WTRSWRSTMUGSL
RU4WTRSWRSTMUGSL
RU5WTRSWRSTMUGSL
MF1WTRSWRSTMUGSL
MF2WTRSWRSTMUGSL
MF3WTRSWRSTMUGSL
MH1WTRSWRSTMUGSL
HD1WTRSWRSTMUGSL
HD2WTRSWRSTMUGSL
C1WTRSWRSTMUGSL
C2WTRSWRSTMUGSL
VC1WTRSWRSTMUGSL
UC1-5WTRSWRSTMUGSL
CA1WTRSWRSTMUGSL
I1WTRSWRSTMUGSL
I2WTRSWRSTMUGSL
I3WTRSWRSEPDITCHOHSLI
I4WELLSWRSEPDITCHOHSLI
P1WTRSWRSTMUGSL
P2WTRSWRSTMUGSL
P3WELLSWRSEPSTMWSLI
P4WELLSWRSEPSTMWSL
W1N/AN/AN/AN/AN/A
W2As Required Based on Development Proposal
CD(3)WTRSWRSTMUGSL
CD12WTRSWRSTMUGSL

Notes:

  1. Comprehensive Development Zones listed in Section 17 of the Zoning Bylaw, except the CD12 – Airport zone.
  2. The zones identified in this table are the zones designated in the Zoning Bylaw. Properties with an 's'. ‘b’. ‘h’, ‘lp’ or ‘rls’ as part of the zoning designation shall comply with the works and services requirements of the parent zone (e.g. RU1s shall comply with the requirements of the RU1 zone.)
Road Requirements

Road requirements (refer to Standard Drawings) are determined using Table 2 below and Section 4.2 – Road Classifications.

Road Classifications
  1. 1. Roadway classifications identified within the Map 13.1 - Functional Road Classification of the City’s Official Community Plan (OCP).
  2. OCP Functional Road Classification Overlays:
  3. Consideration of the local context; the local context may include considerations such as, but not limited to:
    • Fixed elements unlikely to change over time, like topography, water bodies, environmentally sensitive areas, agricultural land reserves, First Nations reserves, etc.
    • Atypical frontages, for example schools, recreational facilities, parks, industrial loading areas, etc.
  4. This Bylaw prescribes infrastructure design and practices. Council recognizes that each situation is unique, and solutions may need to be tailored to the existing conditions. As such, discretion is afforded the City Engineer to ensure the optimal technical solutions are implemented and adapt the prescribed practices herein to suit the individual project/site requirements.
Table 2 - Road Requirements (Refer to Standard Drawings)
Roadway Classification OCP Map 13.1OCP Map 13.3 - Biking OverlayNotes:
Not on Biking OverlayOn Secondary BikingOn Primary Biking Route
LanewayHillsideXS-Ro1Consult with City Engineer 
SuburbanXS-Ro2 
Core AreaXS-Ro2 
Urban CentreXS-Ro2 
LocalRuralXS-R20Consult with City Engineer 
HillsideXS-R21Village Local-Residential, development fronts at least one side
HillsideXS-R22Condition A, development fronts both sides
HillsideXS-R23Condition B, development fronts one side only
HillsideXS-R24Condition C, no development fronts street
SuburbanXS-R25 
IndustrialXS-R26 
Core AreaXS-R27 
Urban CentreXS-R28 
CollectorRuralXS-R40Consult with City Engineer 
HillsideXS-R41Consult with City EngineerVillage Collector Condition A, where commercial development fronts street
HillsideXS-R42Village Collector Condition B, where no commercial development fronts street
HillsideXS-R43Collector Condition A, development fronts both sides
HillsideXS-R44Collector Condition B, development fronts one side only
HillsideXS-R45Collector Condition C, no development fronts street
HillsideXS-R46Minor Collector Condition A, development fronts both sides or, 
development fronts one side only
HillsideXS-R47Minor Collector Condition B, no development fronts street
SuburbanXS-R48XS-R49 
IndustrialXS-R50Consult with City Engineer 
Core AreaXS-R51XS-R52 

Urban Centre

XS-R53XS-R54 
Minor ArterialRuralXS-R60XS-R61 
HillsideXS-R62Consult with City EngineerConsult with City EngineerArterial Condition A, within village centre where environmental conditions 
permit
HillsideXS-R63Arterial Condition B, within 10-minute walking distance of village centre; or, 
within village centre where environmental conditions do not permit the use 
of Condition A
HillsideXS-R64Arterial Condition C, greater than a 10-minute walking distance from 
village centre.
SuburbanXS-R65 
Core AreaXS-R66 
Urban CentreXS-R67 
Major Arterial

Rural 3-Lane

XS-R80XS-R81 
Rural 5-LaneXS-R82XS-R83 
Suburban 3-LaneXS-R84Consult with City Engineer 
Suburban 5-LaneXS-R85 
Core Area 3-LaneXS-R86 
Core Area 5-LaneXS-R87 
Urban Centre 3-LaneXS-R88 
Urban Centre 5-LaneXS-R89 

Notes:

  1. Active Transportation Corridors not located with road right-of-way’s such as but not limited to the Okanagan Rail Trail and Mission Creek Greenway, are transportation corridors requiring frontage improvements.
  2. Pedestrian facilities are required on any road fronting a school or major recreational facility in rural land use areas.
  3. Where a primary Biking Route is identified on OCP Map 13.3 Bike Overlay Map up to 2 m of additional ROW may be required.
  4. Where a Rapid Transit or Frequent Transit Network is identified on OCP Map 13.2 –Transit Overlay up to 3 m of additional ROW may be required on Local, Collector, and Minor Arterial roads and up to 6 m of additional ROW may be required on Major Arterial roads.
  5. Where OCP Maps 13.2, 13.3, 13.4, and 13.5 overlays are present, consult with City Engineer for design requirements.

 

Linear Park Trails Requirements

Linear Park requirements (refer to Standard Drawings) are determined using Table 3: Trail Requirements, Map 10.1 - Linear Corridors of the City’s Official Community Plan (OCP).

Table 3 - Trail Requirements (Refer to Standard Drawings)
ClassDimensionsLongitudinal SlopeCross SlopeMaterials
Trail ClassTrail Type(W) Width(C) Clear Zone(H) Min. Vertical Clearance(S) Typical Slope(S) Slope for Short Sections (max. 10m)Cross SlopeSurface Type(M1) Type Depth(M2) Granular Base

(M3) Sub-Base

(M4) Compacted Sub-Grade
1Major Urban Promenade4.5m or greater0.5m3.0m5% max. (1:20)8% max. (1:12)2% min.Asphalt50mm100mm200mm95% MPD
Concrete or Brick100mm or 75mm100mmN/A95% MPD
2Major Multi-Use (Urban)4.5 - 3.0m0.5m3.0m8% max. (1:12)12% max. (1:8)2% min.Asphalt50mm100mm200mm95% MPD
Concrete or Brick60mm100mmN/A95% MPD
3Major Multi-Use (Rural)4.5 - 3.0m0.5m2.5m8% max. (1:12)12% max. (1:8)2% min.Asphalt50mm75mm150mm95% MPD
Concrete or Brick60mm100mmN/A95% MPD
4Standard Multi-Use3.0 - 2.0m0.5m3.0 - 2.5m8% max. (1:12)15% max. (1:7)2% min.Asphalt millings60mm75mm150mm95% MPD
Aggregate50mm100mmN/A95% MPD
5Narrow Multi-Use1.5 - 1.2m0.5m2.5m8% max. (1:12)15% max. (1:7)2% min.Asphalt millings60mm75mm150mm95% MPD
Aggregate50mm100mmN/A95% MPD
6Nature Trails1.2 - 0.6m0.5m2.5m20% (1:5) max. hiking & walkingOver 20% use steps, etc.2% min.Natural groundN/AN/AN/A95% MPD
15% (1:7) max. mountain biking15%Aggregate if needed50mm100mmN/A95% MPD

Table 3 - Linear Parks Trail Requirements Standard Drawing