Current capital projects

Home > Our community > Planning & projects > Current capital projects

We're working to create vibrant urban centres, a balanced transportation network and an inclusive community. Infrastructure projects improve and maintain outdoor spaces, buildings, active transportation networks, utilities, roads and bridges. 

A fully accessible playground structure will be installed at Strathcona Beach Park this Spring.

Est. start: Spring 2023
Est. end: Summer 2023

The City is constructing Phase 1 of the Aerated Static Pile Composting System.  The composting system will receive municipal yard waste and produce ~143 tonnes/day of...

Est. cost: $8 million
Est. start: Spring 2023
Est. end: Winter 2023

The Altura Rd Fire Flow Watermain Upgrade project will provide a new 200mm diameter PVC main improving Fire Flows to the surrounding homes.

Est. cost: $250,000
Est. start: Spring 2023
Est. end: Spring 2023

Abandon existing infrastructure at Ash Rd site.  Install 400m of watermain and a new, above ground PRV kiosk at the intersection of Viewcrest Rd and Viewcrest Ct.

...
Est. start: Fall 2023
Est. end: Spring 2024

This project was identified as a priority neighbourhood park within the DCC program, as the surrounding area has witnessed significant residential development over the...

Est. cost: $1.56 million
Est. start: Summer 2022
Est. end: Summer 2023
Est. start: Summer 2023
Est. end: Fall 2023

Installation of 150m of Sanitary Sewer on Beaver Lake Rd, extending the existing system from Beaver Lake Ct heading east to the Lake country Wastewater Treatment Plant....

Est. start: Summer 2023
Est. end: Summer 2023

Project overview

Est. start: Spring 2023
Est. end: 2024

The existing storm main carrying Brandt’s Creek has degraded due to root intrusion which requires repairing.

Est. cost: $200,000
Est. start: Summer 2023
Est. end: Fall 2023